Setting up Missing Assignment Exports - Filter Method

Students sometimes forget to turn in assignments. In PowerTeacher Pro teachers can check a box to indicate that the assignment is missing. Schools can also choose to send reminders of missing assignments on a periodic basis. We recommend sending them weekly and ideally not on the last day of the week so that students can be reminded to bring materials home to complete the task rather than be notified after they've already left school for the weekend.

Assumptions

  • The Exclude All option is not selected for the student
  • The Exclude from Missing Assignments exports is not selected for the student
  • Gradebook is PowerTeacher Pro
  • Assignment is not due in the future
  • Assignment was due within the timeframe as set up in the BrightArrow Settings > Filters > Lookup Rules tab > Grading tab
    • Each school can have different settings. If one school uses semesters and another uses quarters both can be accommodated. 

Filters

This export will respect the settings from the BrightArrow Settings area. For more information on how to change the settings read How to Change the Missing Assignments Reminder Filters. Once the export is set up and scheduled all changes other than export time changes can be done from the settings area.

    Setting up Missing Assignment exports

    The export should be set up in DEM from District Office. For information on getting to DEM read Getting to Data Export Manager (DEM)

    1. Category = Additional Data Sets
    2. Export From = BrightArrow Missing Assignments - From Filter
    3. Fields -> Select the checkbox next to "PGFINALGRADES" to select all fields. Fields are already listed in proper order.
    4. Click Next
    5. No filters here, controlled by the settings page filters
    6. Click Next
      Note: Before the next section becomes editable the entire template must run. This is not a quick process and the larger your district the longer this will take.
    7. Export File Name = missing_assignments.txt
    8. Line Delimiter = CR/LF
    9. Character Set = UTF-8
    10. Click Save Template
    11. Name = BrightArrow - Missing Assignments
    12. Click Save as New
    13. Switch to the My Templates tab
    14. Find the row for the new template and click the calendar button to schedule this template. If you do not see the calendar button or the Scheduled System Templates tab you don't have permission to schedule exports. For more information on that read Enabling DEM Scheduling
    15. Days to Execute = Pick a day to run. Thursdays give a chance to notify before the weekend to bring home any materials that might be needed to complete the work
    16. When to Execute = pick a time 5 to 10 minutes before you want the message to go out. There needs to be some processing time for PowerSchool to generate the file and send it to us. If you want the message to go at 10:10am then export at 10:00am.
    17. Send Output To = BrightArrow
    18. Email Completion Report To (optional) = your email or an email to keep a record of if the export and file transfer was successful or if it failed. 
    19. Click Save
    20. Your export will go at the scheduled time and day(s). To send a copy now so that we can get started setting up the import of the file you can click the Send Now button which looks like the Play button from DVD player
    21. Let us know that the file is ready so that we can set up your import
    Did this answer your question? Thanks for the feedback There was a problem submitting your feedback. Please try again later.